Following some technical issues that slowed the progress of the restoration work on the roof of the church in Samoëns, operations are now proceeding without major difficulty. Several elected officials recently visited the site, accompanied by the project manager, the agency D’Ar Jhil. The commencement of slate laying already allows for an assessment of the technical and visual quality of the work, befitting this remarkable edifice, listed as a historic monument since 1987.
The construction site, which has not paused since its start last autumn, is several months behind schedule. The discovery of asbestos in the attics necessitated the prompt implementation of specific administrative procedures for its safe removal, ensuring the safety of both workers and site users. Furthermore, the restoration of the timber frames, dating from 1705, proved more complex than anticipated, requiring the replacement of a greater number of wooden elements.
Today, the replacement of damaged timbers in the nave's roof structure is complete. In recent weeks, the craftsmen also proceeded with laying the battens, which form the support for the slates. Slate laying began in September on the north slope, and more recently on the south slope, with work now advancing simultaneously on both sides. Approximately 60,000 slates will be laid in total. The eight dormer windows, prepared off-site, have also arrived; the first four have been installed on the north slope, and the remaining four will be fitted shortly.
In early October, the four restored stained-glass windows for the dormers will return to the site, followed by four new stained-glass windows that will replace the current single glazing on the dormers facing the Gros Tilleul square. Slate laying will continue until the end of the year. The scaffolding will then be dismantled as soon as conditions permit, though its removal is dependent on the Christmas festivities occupying the place du Gros Tilleul. The restoration of the bell tower will resume in the spring of 2027. The cross, damaged during scaffolding installation, is currently being restored and will be returned to the commune by year-end.