The municipality of Morzine has initiated significant works on the Route de la Combe à Zore, aimed at burying telecommunication, electricity (Enedis), and public lighting networks. These operations, taking place between house numbers 287 and 1018 on the road, are planned in several phases and will span approximately two and a half years, primarily during the shoulder seasons.
The provisional schedule for the works is as follows: Phase 1 is planned for autumn 2026, followed by Phase 2 in spring 2027. Subsequent phases are scheduled for autumn 2027 (Phase 3), spring 2028 (Phase 4), and finally autumn 2028 (Phase 5).
The first phase, concerning the section of the road between numbers 770 and 1018, commenced on September 21, 2026. It will continue until the end of November 2026. During this period, traffic will be managed under an alternating system to ensure the smooth progress of the operations.