The company Sogimm has initiated the construction site for the 'Novaé' real estate development in the municipality of Epagny Metz-Tessy. This ambitious project plans for the construction of 93 housing units spread across three distinct buildings.
Given the technical specifications, particularly the requirement to build two basement levels, this initial phase of the construction involves substantial excavation work. These operations are expected to continue until the end of 2026.
Subsequent phases of the project include the structural work, scheduled to begin in January 2027 and last for just over a year. This will be followed by backfilling and exterior landscaping in the spring of 2027, with the second fix work commencing in February 2028. The projected completion date for the works is September 2028.