The bridge, used daily by approximately 7,700 cars, 300 heavy goods vehicles, and 200 to 400 cyclists, shows concrete cracks in its central span. Following an inspection in April 2026, a temporary repair allowed vehicles to cross, but a replacement of the damaged part is now necessary for a lasting solution.
The complete closure to vehicle traffic will last from November 12 to February 19, 2027, with various work phases. The installation of a footbridge will allow pedestrian and cyclist access, except during certain crane operations.
The works include the diversion of electrical, water, telecommunications, and gas networks. The exact dates for these interventions may change depending on weather conditions or technical issues.
The bridge remains prohibited for vehicles weighing 3.5 tonnes and over.