Work will commence on Monday, October 19, 2026, with the replacement of the school's underground utilities. Connections will be made on Rue de Lyon and Place Rosenau over approximately 7 days. During this period, traffic will be disrupted, and a detour will be implemented.
Following this initial phase, the project will continue with the planting of vegetation, installation of school furniture, resurfacing of grounds, and the creation of various spaces tailored for students. The project's completion is scheduled for late February 2027.
The municipality thanks residents for their understanding and patience during the potential traffic disruptions.